Skip to main content
04-1995-0535JudicialConcludedFY 1995· Region 04

EPA v. GE/SHEPHERD FARM SUPERFUND SITE

Final Order With Specified Cost Recovery

Cost recovery

$1,028,776

Compliance action

$5,000,000

Case summary

SUPERFUND PRN REPORT SENT TO DOJ IN ANTICIPATION OF RD/RA NEGOTIATIONS TOWARDS A CONSENT DECREE. ONE PRP, GENERAL ELECTRIC, WILL BE GIVEN THE OPPORTUNITY TO CONDUCT REMEDY. THE REMEDY IS APPROX $6 MILLION. ONGOING LITIGATION WITH GE AND EPA REGARDING THE NPL LISTING AND GE HAS APPEALED FOIA DENIAL (PENDING IN HEADQUARTERS). 5/29/96 - EPA AND GENERAL ELECTRIC COMPANY REACHED AGREEMENT IN CONSENT DECREE FOR CLEANUP AT GE/SHEPHERD FARM SUPERFUND SITE. ON 5/29/96, THE REGION REFERRED THE CD TO DOJ FOR LODGING AND ENTERING IN DISTRICT COURT.

Defendants (1)

  • GENERAL ELECTRIC COMPANYNamed in complaintNamed in settlement

Facilities (1)

  • GENERAL ELECTRIC LIGHTING SYSTEMS INCORPORATED

    3010 SPARTANBURG HWY., HENDERSONVILLE, NC, 28739

    Registry ID: 110000351565

Statutes cited

  • CERCLA 107ACost Recovery

Enforcement conclusions (1)

  • GENERAL ELECTRIC COMPANYentered 1996-12-02

    Primary law: CERCLA

Timeline (7 milestones)

  • 1995-09-22Enforcement Action Data Entered
  • 1995-09-22PRN Sent
  • 1996-05-29Referred To Dept Of Justice
  • 1996-09-19Complaint Filed With Court
  • 1996-12-02Final Order Lodged
  • 1996-12-02Final Order Entered
  • 1996-12-02Concluded

Case metadata

EPA activity ID
21497
Case number
04-1995-0535
DOJ docket
90-11-3-1561
Lead agency
EPA
HQ division
CER
Branch
CER
EPA region
04
Multimedia
No
Voluntary self-disclosure
No
Primary statute
Cost Recovery

Sourced verbatim from EPA ECHO Enforcement Case Report for case 04-1995-0535 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.