EPA v. KOPPERS CO. INC. (MORRISVILLE PLANT)
Final Order With Specified Cost Recovery
Cost recovery
$1,023,475
Case summary
(1) THIS REFERRAL SETTLES A CERCLA SECTION 107 COST RECOVERY MATTER. EPA INCURRED OVER $1,054,000 IN RI/FS OVERSIGHT AND RD OVERSIGHT COSTS, AS WELL AS ENFORCEMENT RELATED COSTS. THE SITE, A FORMER WOOD TREATING PLANT, HAS SOIL AND GROUNDWATER CONTAMINATION. (2) DEFENDANT: BEAZER EAST, INC. (3) THE CD OBTAINS COST RECOVERY RELIEF UNDER SECTION 107 OF CERCLA, 42 U.S.C. SECTION 9607. (4) OTHER - NOT APPLICABLE.
Defendants (1)
- BEAZER EAST, INC.Named in complaintNamed in settlement
Facilities (1)
BEAZER EAST INC RALEIGH SITE
KOPPERS RD, MORRISVILLE, NC, 27560
Registry ID: 110007657696
Statutes cited
- CERCLA 107A — Cost Recovery
- CERCLA 106A — Imminent & Substantial Endangerment Order
Enforcement conclusions (1)
BEAZER EAST, INC. (04-1995-C023)entered 1995-08-16
Primary law: CERCLA
Timeline (8 milestones)
- 1992-10-01Enforcement Action Data Entered
- 1992-12-15PRN Sent
- 1994-09-20Referred To Dept Of Justice
- 1995-01-26Complaint Filed With Court
- 1995-08-16Concluded
- 1995-08-16Final Order Lodged
- 1995-08-16Final Order Entered
- 1995-09-22Enforcement Action Closed
Case metadata
- EPA activity ID
- 20914
- Case number
- 04-1993-1133
- Lead agency
- EPA
- HQ division
- CER
- Branch
- CER
- EPA region
- 04
- Multimedia
- No
- Voluntary self-disclosure
- No
- Primary statute
- Cost Recovery
Sourced verbatim from EPA ECHO Enforcement Case Report for case 04-1993-1133 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.