Skip to main content
04-1992-0021JudicialConcludedFY 1992· Region 04

EPA v. SANGAMO WESTON/12 MILE CREEK/LAKE HARTWELL OU1

Final Order With Specified Cost Recovery

Cost recovery

$742,796

Case summary

--CD ENTERED 12/03/92-- THE SANGAMO WESTON/TWELVE MILE CREEK/LAKE HARTWELL PCB CONT. SUPERFUND SITE, OPERABLE UNIT NO. 1, CONSENT DECREE PROVIDES FOR THE FINANCING AND IMPLEMENTATION OF RD/RA BY SCHLUMBERGER INDUSTRIES, INC. (SII). IN ADDITION, THE CD REQUIRES SII TO PAY THE AMOUNT OF $792,796.65 IN PAST COST RECOVERY ASSIGNED TO OPERABLE UNIT NO.1, AND ALL FUTURE OVERSIGHT COSTS FOR RD/RA. AS OF SEPTEMBER 15, 1992, THE CD WAS LODGED BUT IT HAS NOT BEEN ENTERED. CASE FILED IN U.S. DISTRICT COURT FOR S.C., ANDERSON DIVISION; CIVIL NO. 8-92-1097-20.

Defendants (1)

  • SCHULMBERGER IND. INC.Named in complaintNamed in settlement

Facilities (1)

  • SCHLUMBERGER INCORPORATED

    313 NORTH HIGHWAY 11, WEST UNION, SC, 296960075

    Registry ID: 110000587721

Statutes cited

  • CERCLA 107ACost Recovery
  • CERCLA 106AImminent & Substantial Endangerment Order

Enforcement conclusions (1)

  • SCHLUMBERGER INDUSTRIES, INC.entered 1992-12-03

    Primary law: CERCLA

Timeline (7 milestones)

  • 1989-09-20Enforcement Action Data Entered
  • 1990-12-27PRN Sent
  • 1992-03-04Referred To Dept Of Justice
  • 1992-12-03Final Order Lodged
  • 1992-12-03Final Order Entered
  • 1992-12-03Complaint Filed With Court
  • 1992-12-03Concluded

Case metadata

EPA activity ID
20754
Case number
04-1992-0021
DOJ docket
90-11-2-696
Lead agency
EPA
HQ division
CER
Branch
CER
EPA region
04
Multimedia
No
Voluntary self-disclosure
No
Primary statute
Cost Recovery

Sourced verbatim from EPA ECHO Enforcement Case Report for case 04-1992-0021 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.