EPA v. SKYLAND HOLDINGS, LLC; LIDI US CORPORATION, LLC AND TEEL CONSTRUCTION (SKYLAND HOLDINGS DEVELOPMENT)

Final Order With Penalty

Case summary

On January 21, 2025, Region 3 entered into a Consent Agreement and Final Order with three operators at an 18-acre mixed development site in southeast Washington, D.C.: Skyland Holdings, LLC ( Skyland ), Lidl US Operations, LLC ( Lidl ) and Teel Construction, Inc. ( Teel ) for unpermitted construction stormwater discharges. The Skyland Holdings construction site is located at 2626 Naylors Road SE, Washington, DC, 20020. From at least March 24, 2022, until August 18, 2022, none of the operators had coverage under the NPDES Construction General Permit for construction activities while Teel built the Lidl grocery store on the site. The construction of the grocery store was part of a Common Plan of Development as defined in Appendix A of the 2022 NPDES Construction Stormwater Permit ( CGP ). The Consent Agreement requires the Respondents to pay a total civil penalty of $39,500.01, with each party paying a third of the penalty ($13,166.67 each). The DC Department of Energy & Environment is being kept informed of this enforcement matter.

Defendants (3)

  • TEEL CONSTRUCTIONNamed in complaintNamed in settlement
  • LIDI US CORPORATION, LLCNamed in complaintNamed in settlement
  • SKYLAND HOLDINGS, LLCNamed in complaintNamed in settlement

Facilities (2)

  • SKYLAND HOLDINGS DEVELOPMENT

    2626 NAYLOR ROAD, SE, WASHINGTON, DC, 20020

    Registry ID: 110070063686

  • SKYLAND

    2626 NAYLOR ROAD, SE, WASHINGTON, DC, 20020

    Registry ID: 110070063686

Statutes cited

  • CWA 301/402NPDES Permit Violations

Enforcement conclusions (1)

  • SKYLAND HOLDINGS, LLC; LIDI US CORPORATION, LLC AND TEEL CONSTRUCTION (SKYLAND HOLDINGS DEVELOPMENT)entered 2025-01-21

    Primary law: CWA

    Federal penalty: $39,500

Timeline (4 milestones)

  • 2025-01-21Final Order Issued
  • 2025-01-21Complaint Filed/Proposed Order
  • 2025-01-28Enforcement Action Data Entered
  • 2025-02-24Enforcement Action Closed

Case metadata

EPA activity ID
3604244191
Case number
03-2025-0010
Lead agency
EPA
EPA region
03
Voluntary self-disclosure
No
Primary statute
NPDES Permit Violations