EPA v. Waco Oil & Gas Co., Inc
Final Order With Penalty
Case summary
On October 5, 2021, EPA referred a civil judicial action to DOJ against Waco Oil & Gas Company, Inc. (?Waco?) for violations of Sections 301 and 404 of the CWA in the form of unauthorized discharges of dredged and/or fill material to waters of the United States in connection with construction of a site for speculative development in Braxton County, West Virginia. Beginning in September 2016, Waco operated equipment that discharged dredged and/or fill material to construct two flat pads and an access road causing direct impacts to 6 separate stream channels, filling 2,059 linear feet of stream and 0.19 acres of wetlands, and causing secondary impacts as a result of the fill of downstream aquatic resources. Waco performed this work without a required permit from the U.S. Army Corps of Engineers, and has a previous history of similar violations at other locations in the state. Waco has so far failed to comply with a unilateral administrative order issued by the Region on February 9, 2021 to develop a restoration plan to adequately address the impacts on-site, and to submit a certificate of temporary stabilization. Through the referral, EPA seeks to require Waco to stabilize the site, submit an adequate restoration plan that includes compensatory mitigation as necessary, and pay a penalty. The West Virginia Department of Environmental Protection was informed of EPA?s intent to refer the matter, and expressed interest in joining the action as a co-plaintiff to bring claims relating to Waco?s violation of its state construction stormwater permit.
Defendants (1)
- Waco Oil & Gas Co. IncNamed in complaintNamed in settlement
Facilities (1)
ROUTE 19 MORRIS DEVELOPMENT (WACO OIL & GAS)
APPROX. 1.25 MILES EAST ON ROUTE 19 FROM I-79, SUTTON, WV, 26601
Registry ID: 110070703618
Statutes cited
- CWA 301 — NPDES Discharge without a Permit
- CWA 404 — Permits for Dredge and Fill Material
Enforcement conclusions (1)
Waco Oil & Gas co., Incentered 2024-02-20
Primary law: CWA
Federal penalty: $412,500 · State/local: $412,500
Timeline (6 milestones)
- 2021-10-04Referred To Dept Of Justice
- 2021-12-01Enforcement Action Data Entered
- 2023-09-28Final Order Lodged
- 2023-09-28Complaint Filed With Court
- 2024-02-20Concluded
- 2024-02-20Final Order Entered
Case metadata
- EPA activity ID
- 3602908952
- Case number
- 03-2022-7001
- Lead agency
- EPA
- EPA region
- 03
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Discharge without a Permit
Sourced verbatim from EPA ECHO Enforcement Case Report for case 03-2022-7001 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.