EPA v. STAMPER, MILTON N. (CENTRAL CHEMICAL SITE)
Final Order With Specified Cost Recovery
Case summary
THE SITE IS LOCATED WITHIN THE CITY LIMITS OF HAGERSTOWN, WASHNGTON COUNTY, MARYLAND. EPA ENTERED A SETTLEMENT AGREEMENT WITH SIXTEEN RESPONDENTS ON AUGUST 23, 2013. FOR THE PAST YEAR, EPA HAS BEEN IN NEGOTIATIONS WITH THE RESPONDENTS FOR PERFORMANCE OF THE REMEDIAL ACTION AND REIMBURSEMENT OF PAST RESPONSE COSTS AT THE SITE. AS WRITTEN, THE SETTLEMENT AGREEMENT WAS TO TERMINATE UPON THE LODGING OF AN RD/RA CONSENT DECREE. THIS AMENDMENT CHANGES THE SETTLEMENT AGREEMENT'S TERMINATION TO BE THE DATE AN RD/RA CONSENT DECREE IS ENTERED IN THE FEDERAL COURT.
Defendants (1)
- STAMPER, MILTON, N.Named in settlement
Facilities (1)
CENTRAL CHEMICAL (HAGERSTOWN)
MITCHELL AVE, HAGERSTOWN, MD, 21742
Registry ID: 110009280214
Statutes cited
- CERCLA 122H — Administrative Cost Recovery Settlement
Enforcement conclusions (2)
STAMPER, MILTON N. (CENTRAL CHEMICAL SITE)entered 2013-10-28
Primary law: CERCLA
STAMPER, MILTON N. (CENTRAL CHEMICAL SITE)entered 2014-09-08
Primary law: CERCLA
Timeline (2 milestones)
- 2013-09-05Enforcement Action Data Entered
- 2014-09-08Final Order Issued
Case metadata
- EPA activity ID
- 3400152448
- Case number
- 03-2013-0146
- Lead agency
- EPA
- EPA region
- 03
- Voluntary self-disclosure
- No
- Primary statute
- Administrative Cost Recovery Settlement
Sourced verbatim from EPA ECHO Enforcement Case Report for case 03-2013-0146 . Bulk data: ICIS-FEC download summary.