EPA v. UPPER ALLEGHENY JOINT SEWER AUTHORITY, ET. AL.
Final Order No Penalty
Case summary
UPPER ALLEGHENY IS IN VIOLATION OF ITS NPDES PERMIT REQUIREMENT TO CONTINUE IMPLEMENTATIONOF THE NMCS AND TO DEVELOP AND IMPLEMENT AN LTCP. UPPER ALLEGHENY CLAIMED INABILITY TO DEVELOP THE LTCP DUE TO LACK OF COOPERATION FROM UNPERMITTED SATELLITE SYSTEMS. EPA HAS ORDERED ALL RESPONDENTS TO WORK TOGETHER SO THE LTCP CAN BE DEVELOPED.
Defendants (7)
- UPPER ALLEGHENY JOINT SEWER AUTHORITYNamed in complaintNamed in settlement
- BUFFALO TOWNSHIPNamed in complaintNamed in settlement
- FAWN TOWNSHIPNamed in complaintNamed in settlement
- BRACKENRIDGE BOROUGHNamed in complaintNamed in settlement
- TARENTUM BOROUGHNamed in complaintNamed in settlement
- HARRISON TOWNSHIPNamed in complaintNamed in settlement
- EAST DEER TOWNSHIPNamed in complaintNamed in settlement
Facilities (1)
UPPER ALLEGHENY WWTP
320 4TH AVENUE, TARENTUM, PA, 15084
Registry ID: 110000762087
Statutes cited
- CWA 301/402 — NPDES Permit Violations
Enforcement conclusions (1)
UPPER ALLEGHENY JOINT SEWER AUTHORITY, ET. AL.entered 2010-01-13
Primary law: CWA
Timeline (2 milestones)
- 2010-01-13Final Order Issued
- 2010-02-03Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 1800074220
- Case number
- 03-2010-0086
- Lead agency
- EPA
- EPA region
- 03
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Permit Violations
Sourced verbatim from EPA ECHO Enforcement Case Report for case 03-2010-0086 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.