EPA v. C & S CONTRACTORS & EQUIPMENT
Final Order With Penalty
Case summary
C&S BEGAN DEMOLITION OF THE FORMER MOBIL GAS STATION WITHOUT FIRST PERFORMING AN ASBESTOS SURVEY AND FILING THE NOTIFICATION FORM W/EPA & PADEP, AS REQUIRED BY 40 CFR 61.145(b). C&S FILED ITS NOTICE LATE.
Defendants (2)
- T/A CROMPTON & SEITZNamed in complaintNamed in settlement
- C&S CONTRACTORS & EQUIPMENT, INC.Named in complaintNamed in settlement
Facilities (1)
C&S CONTRACOTRS & EQUIPMENT, INC.
20 S. WEST END BLVD, QUAKERTOWN, PA, 18951
Registry ID: 110037091875
Statutes cited
- CAA 112B — Asbestos
Enforcement conclusions (1)
C & S CONTRACTORS & EQUIPMENTentered 2008-06-30
Primary law: CAA
Federal penalty: $1,500
Timeline (3 milestones)
- 2008-06-30Final Order Issued
- 2008-06-30Complaint Filed/Proposed Order
- 2008-07-23Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 1000011723
- Case number
- 03-2008-0184
- Lead agency
- EPA
- EPA region
- 03
- Voluntary self-disclosure
- No
- Primary statute
- Asbestos
Sourced verbatim from EPA ECHO Enforcement Case Report for case 03-2008-0184 . Bulk data: ICIS-FEC download summary.