EPA v. Nazcon Concrete Superfund Site
Final Order With Specified Cost Recovery
Case summary
Respondent agreed to pay $15,000 in past response costs. Agreement signed on October 31, 2002, was noticed in Fed Reg on Nov 13, 2002. Comment period closed on December 13, 2002, and Acting RA signed Responsiveness summary on December 16, 2002. Respondent paid agreed-upon recovery to the Superfund on December 31, 2002.
Defendants (1)
- Nazcon Concrete SuperfundNamed in complaintNamed in settlement
Facilities (1)
NACZON CONCRETE SUPERFUND SITE
6500 AMMENDALE RD, BELTSVILLE, MD, 20705
Registry ID: 110001689165
Statutes cited
- CERCLA 122H — Administrative Cost Recovery Settlement
Enforcement conclusions (1)
Nazcon Concrete Superfund Siteentered 2002-12-20
Primary law: CERCLA
Timeline (3 milestones)
- 2002-08-30Enforcement Action Data Entered
- 2002-12-20Complaint Filed/Proposed Order
- 2002-12-20Final Order Issued
Case metadata
- EPA activity ID
- 85190
- Case number
- 03-2002-0255
- Lead agency
- EPA
- EPA region
- 03
- Voluntary self-disclosure
- No
- Primary statute
- Administrative Cost Recovery Settlement