Skip to main content
03-1991-0230JudicialClosedFY 1991· Region 03

EPA v. COOPER INDUSTRIES INC

Final Order With Specified Cost Recovery

Cost recovery

$1,813,687

Case summary

THIS IS A REFERRAL UNDER SECTION 107 OF THE COMPREHENSIVE ENVIRONMENTAL RESPONSE, COMPENSATION, AND LIABILITY ACT OF 1080, AS AMENDED BY THE SUPERFUND AMENDMENTS AND REAUTHOR- IXATION ACT OF 1986, PUB. L. NO. 99-499 (CERCLA), 42 U.S.C. SECTION 9607, FOR RECOUPMENT OF APPROXIMATELY $1.7 MILLION DOLLARS SPENT ON RESPONSE MEASURES UNDERTAKEN AT THE OSBORNE LANDFILL SUPERFUND SITE IN PINE TOWNSHIP, MERCER COUNTYM PA. (OSBORNE SITE OR SITE). EPA ADDITIONALLY SEEKS A DECLARATORY JUDGEMENT UNDER SECTION 113(G)(2) OF CERCAL 42 U.S.C. 9613(G)(2), AND 28 U.S.C. SECTION 2201 FOR LIABIL- ITY FOR FURTHER COSTS TO BE INCURRED AT THE OSBORNE SITE.

Defendants (2)

  • COOPER INDUSTRIES INCNamed in complaintNamed in settlement
  • GENERAL ELECTRIC CONamed in complaintNamed in settlement

Facilities (1)

  • OSBORNE LDFL

    E PINE ST EXT, GROVE CITY, PA, 16127

    Registry ID: 110010585358

Statutes cited

  • CERCLA 107ACost Recovery

Enforcement conclusions (1)

  • COOPER INDUSTRIES, INCentered 1993-03-09

    Primary law: CERCLA

Timeline (7 milestones)

  • 1990-12-01Enforcement Action Data Entered
  • 1991-03-29Referred To Dept Of Justice
  • 1992-12-07Complaint Filed With Court
  • 1993-03-09Final Order Lodged
  • 1993-03-09Final Order Entered
  • 1993-04-08Concluded
  • 1993-04-22Enforcement Action Closed

Case metadata

EPA activity ID
15348
Case number
03-1991-0230
Lead agency
EPA
HQ division
CER
Branch
3RC42
EPA region
03
Multimedia
No
Voluntary self-disclosure
No
Primary statute
Cost Recovery

Sourced verbatim from EPA ECHO Enforcement Case Report for case 03-1991-0230 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.