EPA v. Mirador II LLC
Final Order With Penalty
Case summary
On August 27, 2025, EPA performed a National Pollutant Discharge Elimination System Inspection of the Riviera Multi-Phase Planned Residential Development Construction Project in Bayam?n, Puerto Rico. The findings of the inspection revealed that Respondent did not comply with terms and conditions of the 2022 NPDES Construction General Permit for Discharges from Construction Activities, which constitute a violation of Section 301(a) of the CWA, 33 U.S.C. 1311(a).
Defendants (1)
- Mirador II LLCNamed in complaintNamed in settlement
Facilities (1)
RIVIERA MULTI PHASE PLANNED COMMUNITY
ROAD PR-177, KM 2.2, JUAN SANCHEZ WARD, BAYAMON, PR, 00959
Registry ID: 110070526687
Statutes cited
- CWA 301/402 — NPDES Permit Violations
Enforcement conclusions (1)
Mirador II LLCentered 2026-08-10
Primary law: CWA
Federal penalty: $21,480
Timeline (5 milestones)
- 2026-08-10Complaint Filed/Proposed Order
- 2026-08-10Final Order Issued
- 2026-08-10Enforcement Action Data Entered
- 2026-08-10Enforcement Action Closed
- 2026-08-10NPDES Closed
Case metadata
- EPA activity ID
- 3605043777
- Case number
- 02-2026-3352
- Lead agency
- EPA
- EPA region
- 02
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Permit Violations