EPA v. Hacienda Miramar, Inc./Karimar Construction, Inc.
Final Order With Penalty
Case summary
Consent Agreement and Final Order (CA/FO) in settlement of an enforcement action initiated against the Respondents for violations to Sections 301(a) and 402(p) of the CWA during the construction of the Mirador del Sol residential construction project. Respondents failed to apply and obtain NPDES permit coverage for the stormwater discharges from small construction activities at the project, and the unlawful discharge of pollutants from the project into an unnamed creek, Ci�naga de Cueva and the Caribbean Sea. The CA/FO provides for the payment of a civil penalty of $45,000.
Defendants (1)
- Hacienda Miramar, Inc./Karimar Construction, Inc.Named in complaintNamed in settlement
Facilities (2)
MIRADOR DEL SOL
PR-102 ROAD, KM. 16.5, CABO ROJO, PR, 00623
Registry ID: 110070500969
RIO GRANDE RESIDENTIAL PROJECT
ROAD PR-115 KM. 17.6, WARD RIO GRANDE, RINCON, PR, 00677
Registry ID: 110070556055
Statutes cited
- CWA 301/402 — NPDES Permit Violations
- CWA 301 — NPDES Discharge without a Permit
Enforcement conclusions (1)
Hacienda Miramar, Inc./Karimar Construction, Inc.entered 2023-03-27
Primary law: CWA
Federal penalty: $45,000
Timeline (4 milestones)
- 2022-09-30Complaint Filed/Proposed Order
- 2022-10-04Enforcement Action Data Entered
- 2023-03-27Enforcement Action Closed
- 2023-03-27Final Order Issued
Case metadata
- EPA activity ID
- 3603372166
- Case number
- 02-2022-3451
- Lead agency
- EPA
- EPA region
- 02
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Permit Violations