EPA v. Energy Transfer Eagle Point Terminal
Final Order No Penalty
Case summary
Respondent failed to complete the stack testing of its new vapor combustion unit within the required 180 days of start-up. The order requires the facility to complete the stack testing by July 5, 2022.
Defendants (1)
- Energy Transfer Eagle Point TerminalNamed in settlement
Facilities (4)
EAGLE POINT TERMINALS LLC (EP TERMINAL)
1000 CROWN POINT RD, WESTVILLE, NJ, 08093
Registry ID: 110025330728
EAGLE POINT TERMINALS LLC (EP TERMINAL)
1000 CROWN POINT RD, WESTVILLE, NJ, 08093
Registry ID: 110025330728
EAGLE POINT TERMINALS LLC (EP TERMINAL)
1000 CROWN POINT RD, WESTVILLE, NJ, 08093
Registry ID: 110025330728
EAGLE POINT TERMINALS LLC (EP TERMINAL)
1000 CROWN POINT RD, WESTVILLE, NJ, 08093
Registry ID: 110025330728
Statutes cited
- CAA 112D — MACT Standards
Enforcement conclusions (1)
Energy Transfer Eagle Point Terminalentered 2022-06-13
Primary law: CAA
Timeline (4 milestones)
- 2022-06-13Final Order Issued
- 2022-06-13Air Resolved
- 2022-06-13Enforcement Action Closed
- 2022-06-24Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 3603261784
- Case number
- 02-2022-1005
- Lead agency
- EPA
- EPA region
- 02
- Voluntary self-disclosure
- No
- Primary statute
- MACT Standards
Sourced verbatim from EPA ECHO Enforcement Case Report for case 02-2022-1005 . Bulk data: ICIS-FEC download summary.