Skip to main content
02-2022-1005Administrative - FormalClosedFY 2022· Region 02

EPA v. Energy Transfer Eagle Point Terminal

Final Order No Penalty

Case summary

Respondent failed to complete the stack testing of its new vapor combustion unit within the required 180 days of start-up. The order requires the facility to complete the stack testing by July 5, 2022.

Defendants (1)

  • Energy Transfer Eagle Point TerminalNamed in settlement

Facilities (4)

  • EAGLE POINT TERMINALS LLC (EP TERMINAL)

    1000 CROWN POINT RD, WESTVILLE, NJ, 08093

    Registry ID: 110025330728

  • EAGLE POINT TERMINALS LLC (EP TERMINAL)

    1000 CROWN POINT RD, WESTVILLE, NJ, 08093

    Registry ID: 110025330728

  • EAGLE POINT TERMINALS LLC (EP TERMINAL)

    1000 CROWN POINT RD, WESTVILLE, NJ, 08093

    Registry ID: 110025330728

  • EAGLE POINT TERMINALS LLC (EP TERMINAL)

    1000 CROWN POINT RD, WESTVILLE, NJ, 08093

    Registry ID: 110025330728

Statutes cited

  • CAA 112DMACT Standards

Enforcement conclusions (1)

  • Energy Transfer Eagle Point Terminalentered 2022-06-13

    Primary law: CAA

Timeline (4 milestones)

  • 2022-06-13Final Order Issued
  • 2022-06-13Air Resolved
  • 2022-06-13Enforcement Action Closed
  • 2022-06-24Enforcement Action Data Entered

Case metadata

EPA activity ID
3603261784
Case number
02-2022-1005
Lead agency
EPA
EPA region
02
Voluntary self-disclosure
No
Primary statute
MACT Standards