EPA v. Township of Edison (MS4)
Final Order With Penalty
Case summary
On September 20 - 22, 2016, the EPA conducted a Municipal Separate Storm Sewer System (MS4) Audit of the Township of Edison and identified that the Township was not complying with the terms and conditions of the NJDEP Tier A Municipal Stormwater General Permit. This Consent Agreement and Final Order includes a $7,500 penalty.
Defendants (1)
- Township of EdisonNamed in complaintNamed in settlement
Facilities (1)
EDISON TWP
100 MUNICIPAL BLVD, EDISON, NJ, 088173399
Registry ID: 110015109345
Statutes cited
- CWA 301/402 — NPDES Permit Violations
Enforcement conclusions (1)
Township of Edison (MS4)entered 2019-04-24
Primary law: CWA
Federal penalty: $7,500
Timeline (5 milestones)
- 2019-04-24Final Order Issued
- 2019-04-24NPDES Closed
- 2019-04-24Complaint Filed/Proposed Order
- 2019-04-24Enforcement Action Closed
- 2019-04-26Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 3601823152
- Case number
- 02-2019-3306
- Lead agency
- EPA
- EPA region
- 02
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Permit Violations
Sourced verbatim from EPA ECHO Enforcement Case Report for case 02-2019-3306 . Bulk data: ICIS-FEC download summary.