EPA v. Bordentown Township
Unilateral Administrative Order Without Adjudication
Case summary
Respondent is a permitted Phase II MS4 in New Jersey. An MS4 inspection was conducted on June 12 ? 13, 2018. As a result of the inspection, it was determined that the Respondent was not complying with the NJDEP Tier A Municipal General Stormwater Permit. Violations include, but are not limited to, failure to update the Stormwater Pollution Prevention Plan, failure to have a current outfall pipe map, failure to document inspections of maintenance yards, failure to have a formal program that documents long-term operation and maintenance for publicly owned best management practices, and failure to have the Stormwater Pollution Prevention Plan and Municipal Stormwater Management Plan posted on Respondent's website by 4/1/2018 as required by the Permit. An Information Request and Administrative Compliance Order is being issued to order Respondent to comply with the Tier A Municipal General Permit conditions.
Defendants (1)
- Bordentown TownshipNamed in settlement
Facilities (1)
BORDENTOWN TWP
1 MUNICIPAL DR, BORDENTOWN TWP, NJ, 08505
Registry ID: 110015013297
Statutes cited
- CWA 301/402 — NPDES Permit Violations
Enforcement conclusions (1)
Bordentown Townshipentered 2018-07-25
Primary law: CWA
Timeline (4 milestones)
- 2018-07-25Final Order Issued
- 2018-08-14Enforcement Action Data Entered
- 2020-03-20Enforcement Action Closed
- 2020-03-20NPDES Closed
Case metadata
- EPA activity ID
- 3601518884
- Case number
- 02-2018-3040
- Lead agency
- EPA
- EPA region
- 02
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Permit Violations