EPA v. Kaplan Companies
Final Order No Penalty
Case summary
This administrative order on consent is being issued in conjunction with an administrative penalty order, CWA-02-2018-3401, which together resolve violations at four (4) construction sites in New Jersey and require the Respondent to implement a company-wide stormwater compliance program at its construction sites.
Defendants (1)
- Kaplan CompaniesNamed in settlement
Facilities (4)
WOODFIELD
MT. OLIVE IIIA, SOWERS DRIVE, MT. OLIVE, NJ, 07840
Registry ID: 110067644302
GATEWAY AT CARTERET
ROOSEVELT AVENUE, MIDDLESEX, NJ, 07008
Registry ID: 110064507298
POINT OF WOODS
ROUTE 1 & NEW ROAD, SOUTH BRUNSWICK, NJ, 08852
Registry ID: 110067437704
LAMER PHASE VI
WOODLAKE DRIVE AND FERNANDEZ COURT, SAYERVILLE, NJ, 08872
Registry ID: 110067441129
Statutes cited
- CWA 301/402 — NPDES Permit Violations
Enforcement conclusions (1)
Kaplan Companiesentered 2018-05-29
Primary law: CWA
Timeline (4 milestones)
- 2018-05-29NPDES Closed
- 2018-05-29Enforcement Action Closed
- 2018-05-29Final Order Issued
- 2018-07-24Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 3601502076
- Case number
- 02-2018-3031
- Lead agency
- EPA
- EPA region
- 02
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Permit Violations
Sourced verbatim from EPA ECHO Enforcement Case Report for case 02-2018-3031 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.