EPA v. 155 Third Street, LLC et al.
Final Order With Unspecified Cost Recovery
Case summary
The Agreement calls for the performance of a removal action to replace a collapsed, deteriorated bulkhead at 155 3rd Street, Brooklyn, in connection with the redevelopment of the property. The facility's bulkhead is in poor condition. The replacement bulkhead has been designed to EPA's specifications, such that its increased depth will obviate the need for temporary shoring during future dredging of contaminated canal sediments, reducing overall project costs and time. The bulkhead repair work will require re-suspension controls to limit disturbance of contaminated canal sediments. The value of the work is approximately $1,000,000. Respondent will also reimburse EPA for its costs of overseeing the work.
Defendants (2)
- Monadnock Construction, Inc.Named in settlement
- 155 Third Street, LLCNamed in settlement
Facilities (1)
GOWANUS CANAL
BUTLER ST (BETWEEN BOND ST AND NEVINS ST, BROOKLYN, NY, 11231
Registry ID: 110033604197
Statutes cited
- CERCLA 107A — Cost Recovery
- CERCLA 106A — Imminent & Substantial Endangerment Order
Enforcement conclusions (1)
155 Third Street, LLC et al.entered 2017-03-29
Primary law: CERCLA
Timeline (3 milestones)
- 2017-03-29Final Order Issued
- 2017-03-29Enforcement Action Closed
- 2017-04-04Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 3600995157
- Case number
- 02-2017-2010
- Lead agency
- EPA
- EPA region
- 02
- Voluntary self-disclosure
- No
- Primary statute
- Cost Recovery