EPA v. 163 6th Street LLC
Final Order With Unspecified Cost Recovery
Case summary
The Agreement calls for the performance of a removal action to replace a collapsed, deteriorated bulkhead at 163 6th Street, Brooklyn, in connection with the redevelopment of the property as a public storage center. The facility's bulkhead is in moderate condition. The replacement bulkhead has been designed to EPA's specifications, such that its increased depth will obviate the need for temporary shoring during future dredging of contaminated canal sediments, reducing overall project costs and time. Respondent will also install a separated stormwater oil/water control system. The bulkhead repair work will require re-suspension controls to limit disturbance of contaminated canal sediments. The value of the work is approximately $1,000,000. Respondent will also reimburse EPA for its costs of overseeing the work.
Defendants (1)
- 163 6th Street LLCNamed in settlement
Facilities (1)
GOWANUS CANAL
BUTLER ST (BETWEEN BOND ST AND NEVINS ST, BROOKLYN, NY, 11231
Registry ID: 110033604197
Statutes cited
- CERCLA 107A — Cost Recovery
- CERCLA 106A — Imminent & Substantial Endangerment Order
Enforcement conclusions (1)
163 6th Street LLCentered 2016-11-18
Primary law: CERCLA
Timeline (3 milestones)
- 2016-11-18Final Order Issued
- 2016-11-18Enforcement Action Closed
- 2016-11-22Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 3600858349
- Case number
- 02-2017-2001
- Lead agency
- EPA
- EPA region
- 02
- Voluntary self-disclosure
- No
- Primary statute
- Cost Recovery
Sourced verbatim from EPA ECHO Enforcement Case Report for case 02-2017-2001 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.