EPA v. Kaplan Companies - Point of Woods
Unilateral Administrative Order Without Adjudication
Case summary
EPA conducted an inspection at the Point of Woods construction site on February 3, 2016 and identified violations of the New Jersey Pollutant Discharge Elimination System (NJPDES) 5G3 - Construction Activity Storm Water General Permit (CGP), including failure to implement the erosion & sediment control component of the Stormwater Pollution Prevention Plan (SPPP), and failure to conduct site inspections in accordance with the requirements in the CGP. The Order requires Respondent to comply with the terms and conditions of the CGP.
Defendants (1)
- Kaplan Companies - Point of WoodsNamed in settlement
Facilities (1)
POINT OF WOODS
ROUTE 1 & NEW ROAD, SOUTH BRUNSWICK, NJ, 08852
Registry ID: 110067437704
Statutes cited
- CWA 301 — NPDES Discharge without a Permit
- CWA 301/402 — NPDES Permit Violations
Enforcement conclusions (1)
Kaplan Companies - Point of Woodsentered 2016-04-26
Primary law: CWA
Timeline (4 milestones)
- 2016-04-26Enforcement Action Closed
- 2016-04-26Final Order Issued
- 2016-04-26NPDES Closed
- 2016-09-16Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 3600805646
- Case number
- 02-2016-3033
- Lead agency
- EPA
- EPA region
- 02
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Discharge without a Permit
Sourced verbatim from EPA ECHO Enforcement Case Report for case 02-2016-3033 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.