EPA v. Byram Concrete and Supply Inc.
Unilateral Administrative Order Without Adjudication
Case summary
Violations were found during a routine CEI, and the facility failed to implement a best management practice to comply with the approved SWPPP. Complying actions will be to implement containment measures outlined in the approved plan to reduce untreated storm water from entering the storm drain.
Defendants (1)
- Byram Concrete and Supply Inc.Named in settlement
Facilities (1)
BYRAM CONCRETE & SUPPLY
145 VIRGINIA RD, WHITE PLAINS, NY, 10603
Registry ID: 110017885074
Statutes cited
- CWA 301 — NPDES Discharge without a Permit
- CWA 301/402 — NPDES Permit Violations
Enforcement conclusions (1)
Byram Concrete and Supply Inc.entered 2015-12-30
Primary law: CWA
Timeline (4 milestones)
- 2015-12-30Enforcement Action Closed
- 2015-12-30Final Order Issued
- 2015-12-30NPDES Closed
- 2016-03-29Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 3600676455
- Case number
- 02-2016-3020
- Lead agency
- EPA
- EPA region
- 02
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Discharge without a Permit
Sourced verbatim from EPA ECHO Enforcement Case Report for case 02-2016-3020 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.