EPA v. Virgin Islands Water and Power Authority - Richmond

Final Order No Penalty

Case summary

The Respondent failed to apply for a permit, or to modify its existing NPDES Permit to incorporate discrete conveyances of storm water associated with a regulated industrial activity. Respondent failed to fully develop and implement procedures required by its NPDES to effect Best Management Practices for the prevention or minimization of discharge of pollutants at its permitted outfalls. Relief requested includes an a) engineering evaluation of the management of storm water impacting the Facility, in light of structural changes that have occurred in the footprint of the Facility, and how such changes have affected the hydrology and hydraulic character of the Facility in its present developed state; b) design and construct an appropriate structure with roof covering, secondary containment for proper storage and adequate management of bulk quantities of oils, other lubricants, solvents, and chemicals associated with the manufacturing processes. The structure must feature appropriate drainage to manage roof catchment, storm runoff flows, and to address spilled materials; c) permanently remove and ship off-island within 90 days, through a contract entered into with an identified appropriate contractor, all spent transformer units and related wastes that were temporarily relocated to a suitable storage area.

Defendants (1)

  • Virgin Islands Water and Power AuthorityNamed in settlement

Facilities (4)

  • V.I. WATER & POWER AUTHORITY

    ESTATE RICHMOND, ST. CROIX, VI, 00821

    Registry ID: 110000602866

  • V.I. WATER & POWER AUTHORITY

    ESTATE RICHMOND, ST. CROIX, VI, 00821

    Registry ID: 110000602866

  • V.I. WATER & POWER AUTHORITY

    ESTATE RICHMOND, ST. CROIX, VI, 00821

    Registry ID: 110000602866

  • V.I. WATER & POWER AUTHORITY

    ESTATE RICHMOND, ST. CROIX, VI, 00821

    Registry ID: 110000602866

Statutes cited

  • CWA 301/402NPDES Permit Violations
  • CWA 301NPDES Discharge without a Permit

Enforcement conclusions (1)

  • Virgin Islands Water and Power Authority - Richmondentered 2015-07-28

    Primary law: CWA

Timeline (4 milestones)

  • 2015-07-28NPDES Closed
  • 2015-07-28Enforcement Action Closed
  • 2015-07-28Final Order Issued
  • 2015-10-12Enforcement Action Data Entered

Case metadata

EPA activity ID
3600402767
Case number
02-2015-3108
Lead agency
EPA
EPA region
02
Voluntary self-disclosure
No
Primary statute
NPDES Permit Violations