EPA v. Municipality of Guaynabo et al.
Unilateral Administrative Order Without Adjudication
Case summary
COMPLIANCE ORDER ISSUED TO OWNER AND GENERAL CONTRACTOR FOR FAILURE TO OBTAIN NPDES PERMIT COVERAGE FOR ITS STORM WATER DISCHARGES FROM CONSTRUCTION ACTIVITIES INTO THE GUAYNABO RIVER.
Defendants (2)
- Municipality of GuaynaboNamed in settlement
- L.P.C. & D., Inc.Named in settlement
Facilities (1)
CONECTOR LOS FILTROS CONSTRUCTION PROJECT
BETWEEN ROAD PR-833 AND ROAD PR-199, GUAYNABO, PR, 00000
Registry ID: 110063611319
Statutes cited
- CWA 301/402 — NPDES Permit Violations
- CWA 301 — NPDES Discharge without a Permit
Enforcement conclusions (1)
Municipality of Guaynabo et al.entered 2014-12-18
Primary law: CWA
Timeline (4 milestones)
- 2014-12-18NPDES Closed
- 2014-12-18Final Order Issued
- 2014-12-18Enforcement Action Closed
- 2015-04-01Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 3600107330
- Case number
- 02-2015-3105
- Lead agency
- EPA
- EPA region
- 02
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Permit Violations
Sourced verbatim from EPA ECHO Enforcement Case Report for case 02-2015-3105 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.