Skip to main content
02-2015-3105Administrative - FormalClosedFY 2015· Region 02

EPA v. Municipality of Guaynabo et al.

Unilateral Administrative Order Without Adjudication

Case summary

COMPLIANCE ORDER ISSUED TO OWNER AND GENERAL CONTRACTOR FOR FAILURE TO OBTAIN NPDES PERMIT COVERAGE FOR ITS STORM WATER DISCHARGES FROM CONSTRUCTION ACTIVITIES INTO THE GUAYNABO RIVER.

Defendants (2)

  • Municipality of GuaynaboNamed in settlement
  • L.P.C. & D., Inc.Named in settlement

Facilities (1)

  • CONECTOR LOS FILTROS CONSTRUCTION PROJECT

    BETWEEN ROAD PR-833 AND ROAD PR-199, GUAYNABO, PR, 00000

    Registry ID: 110063611319

Statutes cited

  • CWA 301/402NPDES Permit Violations
  • CWA 301NPDES Discharge without a Permit

Enforcement conclusions (1)

  • Municipality of Guaynabo et al.entered 2014-12-18

    Primary law: CWA

Timeline (4 milestones)

  • 2014-12-18NPDES Closed
  • 2014-12-18Final Order Issued
  • 2014-12-18Enforcement Action Closed
  • 2015-04-01Enforcement Action Data Entered

Case metadata

EPA activity ID
3600107330
Case number
02-2015-3105
Lead agency
EPA
EPA region
02
Voluntary self-disclosure
No
Primary statute
NPDES Permit Violations

Sourced verbatim from EPA ECHO Enforcement Case Report for case 02-2015-3105 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.