02-2015-3047Administrative - FormalClosedFY 2015· Region 02

EPA v. City of Camden

Final Order No Penalty

Case summary

This AO amends AO CWA-02-2014-3038 by memorializing the implementation schedule for a series of combined sewer system improvement projects and for the submission of certain elements of the Operation and Maintenance plan. This amendment does not increase either the pollutant loading estimate or injunctive relief estimate used in the development of CWA-02-2014-3038.

Defendants (1)

  • City of CamdenNamed in settlement

Facilities (1)

  • CAMDEN CITY

    CAMDEN CITY, CAMDEN CITY, NJ, 08101

    Registry ID: 110009836874

Statutes cited

  • CWA 301/402NPDES Permit Violations

Enforcement conclusions (1)

  • City of Camdenentered 2015-03-31

    Primary law: CWA

Timeline (4 milestones)

  • 2015-03-31NPDES Closed
  • 2015-03-31Enforcement Action Closed
  • 2015-03-31Final Order Issued
  • 2015-04-01Enforcement Action Data Entered

Case metadata

EPA activity ID
3600107809
Case number
02-2015-3047
Lead agency
EPA
EPA region
02
Voluntary self-disclosure
No
Primary statute
NPDES Permit Violations