EPA v. T.C. Dunham Paint Company, Inc.
Final Order With Specified Cost Recovery
Case summary
On July 14, 2015, the EPA issued a demand for payment of $21,273.12 to the Settling Party for the full amount of response costs incurred by EPA at or connection with the site, as of April 30, 2015.
Defendants (1)
- T.C. Dunham Paint Company, Inc.Named in settlement
Facilities (1)
T.C. DUNHAM PAINT CO. WAREHOUSE
523 SAWMILL RIVER ROAD, YONKERS, NY, 10710
Registry ID: 110046120746
Statutes cited
- CERCLA 107A — Cost Recovery
- CERCLA 122H — Administrative Cost Recovery Settlement
Enforcement conclusions (1)
T.C. Dunham Paint Company, Inc.entered 2015-08-13
Primary law: CERCLA
Timeline (3 milestones)
- 2015-08-13Enforcement Action Closed
- 2015-08-13Final Order Issued
- 2015-08-25Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 3600224654
- Case number
- 02-2015-2024
- Lead agency
- EPA
- EPA region
- 02
- Voluntary self-disclosure
- No
- Primary statute
- Cost Recovery