02-2015-1211Administrative - FormalClosedFY 2015· Region 02

EPA v. E.I DuPont de Nemours and Company

Final Order With Penalty

Case summary

The case was taken in response to an explosion at the plant in November 2011. It was determined that the facility did not act in accordance with the requirements of the General Duty Clause - Section 112r(1).

Defendants (1)

  • E.I DuPont de Nemours and CompanyNamed in complaintNamed in settlement

Facilities (1)

  • E I DUPONT DE NEMOURS - YERKES PLANT

    3115 RIVER RD, BUFFALO, NY, 14207

    Registry ID: 110007997953

Statutes cited

  • CAA 112[R][1]Prevention of Accidental Release/General Duty Clause

Enforcement conclusions (1)

  • E.I DuPont de Nemours and Companyentered 2015-09-30

    Primary law: CAA

    Federal penalty: $723,438 · SEP: $111,953

Timeline (4 milestones)

  • 2015-09-30Final Order Issued
  • 2015-09-30Enforcement Action Closed
  • 2015-09-30Complaint Filed/Proposed Order
  • 2015-10-05Enforcement Action Data Entered

Case metadata

EPA activity ID
3600398902
Case number
02-2015-1211
Lead agency
EPA
EPA region
02
Voluntary self-disclosure
No
Primary statute
Prevention of Accidental Release/General Duty Clause