EPA v. Morgan Stanley et al.
Final Order With Penalty
Case summary
Respondent did not have Cathodic Protection on their piping system. FC was issued and facility failed to come into compliance. FC was withdrawn on January 25, 2012. Pre-filing Settlement letter was issued on March 27, 2014 and a Pre-Settlement meeting was held on May 15, 2014. Respondent removed two of the old tanks and was in the process of removing the other two. Only one tank was to be used for back-up generation and that was placed above ground. Respondent never came into compliance until December 2013. Facility is now in compliance.
Defendants (2)
- Morgan StanleyNamed in complaintNamed in settlement
- Dan PuglieseNamed in complaintNamed in settlement
Facilities (1)
MORGAN STANLEY
2000 WESTCHESTER AVE, PURCHASE, NY, 10577
Registry ID: 110008038088
Statutes cited
- RCRA 9003 — UST Release Detection, Prevention, Correction Regulations
Enforcement conclusions (1)
Morgan Stanley et al.entered 2014-08-27
Primary law: RCRA
Federal penalty: $10,000
Timeline (4 milestones)
- 2014-08-27Enforcement Action Closed
- 2014-08-27Final Order Issued
- 2014-08-27Complaint Filed/Proposed Order
- 2014-09-17Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 3400288131
- Case number
- 02-2014-7502
- Lead agency
- EPA
- EPA region
- 02
- Voluntary self-disclosure
- No
- Primary statute
- UST Release Detection, Prevention, Correction Regulations