EPA v. UTA of KJ, Inc. (United Talmudical Academy of Kiryas Joel) Boy School
Final Order With Penalty
Case summary
The Respondent failed to obtain construction stormwater permit coverage as required. The site is a 2+ acre construction site adjacent to surface waters and discharges to Highland Brook. The discharges associated with construction have been documented. The facility has obtained permit coverage, began inspections and has achieved compliance.
Defendants (1)
- UTA of KJ, Inc.Named in complaintNamed in settlement
Facilities (1)
UNITED TALMUDIC ACADEMY OF KIRYAS JOEL
BAKERTOWN ROAD, KIRYAS JOEL, NY, 10950
Registry ID: 110055166458
Statutes cited
- CWA 301 — NPDES Discharge without a Permit
- CWA 301/402 — NPDES Permit Violations
Enforcement conclusions (1)
UTA of KJ, Inc. (United Talmudical Academy of Kiryas Joel) Boy Schoolentered 2015-04-21
Primary law: CWA
Federal penalty: $113,023
Timeline (5 milestones)
- 2014-09-03Enforcement Action Data Entered
- 2014-09-03Complaint Filed/Proposed Order
- 2015-04-21NPDES Closed
- 2015-04-21Final Order Issued
- 2015-04-21Enforcement Action Closed
Case metadata
- EPA activity ID
- 3400282650
- Case number
- 02-2014-3401
- Lead agency
- EPA
- EPA region
- 02
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Discharge without a Permit
Sourced verbatim from EPA ECHO Enforcement Case Report for case 02-2014-3401 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.