EPA v. Mack Studios
Unilateral Administrative Order Without Adjudication
Case summary
Respondent owns and operates the Mack Studios construction site located in Auburn, NY. EPA conducted a Compliance Evaluation Inspection (CEI) at the site on May 16, 2014. At the time of the CEI, approximately 4 acres of soil were disturbed. A turbid stormwater discharge was identified flowing from the site and was conveyed to wetlands hydraulically connected to the Owasco Outlet. Respondent failed to comply with the conditions of its NYSDEC SPDES Construction General Permit by, among other things, failing to implement and maintain erosion and sediment control measures specified in its SWPPP, failing to implement corrective actions subsequent to inspection notifications, and failing to maintain records on-site. The Administrative Order requires the Respondent to comply with its SPDES Construction General Permit.
Defendants (1)
- Mack StudiosNamed in settlement
Facilities (1)
MACK STUDIOS INC.
5500 TECH PARK BLVD., AUBURN, NY, 13021
Registry ID: 110040142477
Statutes cited
- CWA 301/402 — NPDES Permit Violations
Enforcement conclusions (1)
Mack Studiosentered 2014-07-02
Primary law: CWA
Timeline (4 milestones)
- 2014-07-02NPDES Closed
- 2014-07-02Final Order Issued
- 2014-07-02Enforcement Action Closed
- 2014-09-30Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 3400293257
- Case number
- 02-2014-3047
- Lead agency
- EPA
- EPA region
- 02
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Permit Violations
Sourced verbatim from EPA ECHO Enforcement Case Report for case 02-2014-3047 . Bulk data: ICIS-FEC download summary.