Skip to main content
02-2012-3312Administrative - FormalClosedFY 2012· Region 02

EPA v. Kaplan & Sons Construction Corp.

Final Order With Penalty

Case summary

Respondent is the owner and operator of Phases 5 and 6 of the La Mer development located off of Ernston Road in Sayreville, NJ. The Respondent failed to comply with the New Jersey Department of Environmental Protection (NJDEP) General Permit for Stormwater Discharges associated with Construction Activity, including failure to install and/or properly implement and maintain stormwater Best Management Practice (BMPs) at Phases 5 and 6 of the Site. Stormwater discharges from the Site drain to Cheesequake Creek.

Defendants (1)

  • Kaplan and Sons Construction Corp.Named in complaintNamed in settlement

Facilities (1)

  • LA MER PHASE 5 AND 6

    GIORDANO AVENUE, SAYREVILLE, NJ, 08859

    Registry ID: 110046288003

Statutes cited

  • CWA 301/402NPDES Permit Violations

Enforcement conclusions (1)

  • Kaplan & Sons Construction Corp.entered 2013-01-25

    Primary law: CWA

    Federal penalty: $28,000

Timeline (4 milestones)

  • 2012-09-19Complaint Filed/Proposed Order
  • 2012-09-25Enforcement Action Data Entered
  • 2013-01-25Final Order Issued
  • 2013-01-25Enforcement Action Closed

Case metadata

EPA activity ID
3000062797
Case number
02-2012-3312
Lead agency
EPA
Branch
WGL
EPA region
02
Voluntary self-disclosure
No
Primary statute
NPDES Permit Violations

Sourced verbatim from EPA ECHO Enforcement Case Report for case 02-2012-3312 . Bulk data: ICIS-FEC download summary.