Skip to main content
02-2011-7929Administrative - FormalClosedFY 2011· Region 02

EPA v. Fahs Construction Group, Inc. et al.

Final Order With Penalty

Case summary

Failure to provide overfill prevention, failure to have annual line tightness test or monthly monitoring of pressurized tanks, failure to provide adequate line leak detector system for underground pipes. FC issued. Facility came into compliance 1/11/11.

Defendants (2)

  • Fahs Construction Group, Inc.Named in complaintNamed in settlement
  • Pierce Creek Realty and DevelopmentNamed in complaintNamed in settlement

Facilities (1)

  • FAHS CONSTRUCTION GROUP INC.

    2224 PIERCE CREEK ROAD, BINGHAMTON, NY, 13903

    Registry ID: 110028211959

Statutes cited

  • RCRA 9003UST Release Detection, Prevention, Correction Regulations

Enforcement conclusions (1)

  • Fahs Construction Group, Inc. et al.entered 2011-01-14

    Primary law: RCRA

    Federal penalty: $840

Timeline (4 milestones)

  • 2011-01-14Complaint Filed/Proposed Order
  • 2011-01-14Enforcement Action Closed
  • 2011-01-14Final Order Issued
  • 2011-03-01Enforcement Action Data Entered

Case metadata

EPA activity ID
2600000768
Case number
02-2011-7929
Lead agency
EPA
Branch
WTS
EPA region
02
Voluntary self-disclosure
No
Primary statute
UST Release Detection, Prevention, Correction Regulations

Sourced verbatim from EPA ECHO Enforcement Case Report for case 02-2011-7929 . Bulk data: ICIS-FEC download summary.