EPA v. K-Land No. 57, LLC
Final Order With Penalty
Case summary
Respondent gained coverage under the NJDEP CGP and began construction on 5/22/2009, disturbing over 10 acres of land at the Village at Cinnaminson construction site located in Cinnaminson, New Jersey. Respondent failed to conduct and document weekly site inspections and failed to maintain stormwater BMPs, as required by the CGP.
Defendants (1)
- K-Land No. 57, LLCNamed in complaintNamed in settlement
Facilities (1)
NVR - RYAN HOMES
433 RIVER ROAD, HIGHLAND PARK,, NJ, 08904
Registry ID: 110039517911
Statutes cited
- CWA 301/402 — NPDES Permit Violations
Enforcement conclusions (1)
K-Land No. 57, LLCentered 2010-12-07
Primary law: CWA
Federal penalty: $9,000
Timeline (4 milestones)
- 2010-12-07Final Order Issued
- 2010-12-07Enforcement Action Closed
- 2010-12-07Complaint Filed/Proposed Order
- 2010-12-09Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 2200033188
- Case number
- 02-2011-3309
- Lead agency
- EPA
- Branch
- WGL
- EPA region
- 02
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Permit Violations
Sourced verbatim from EPA ECHO Enforcement Case Report for case 02-2011-3309 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.