EPA v. Minoa Farms LLC
Final Order With Penalty
Case summary
Respondent started construction on 1/5/2009, disturbing over 67 acres of land and failed to comply with the CGP. An NOI was submitted on 3/19/2004; permit coverage was obtained. Based on a 2/23/2010 letter, the site was stabilized pending and future work. Penalty has been calculated for SWPPP and BMP deficiencies.
Defendants (1)
- Minoa Farms, LLCNamed in complaintNamed in settlement
Facilities (1)
MINOA FARMS SUBDIVISION
WEST SIDE BAIRD ST & S HULBER ST, MANLIUS, NY, 13104
Registry ID: 110019383923
Statutes cited
- CWA 301/402 — NPDES Permit Violations
Enforcement conclusions (1)
Minoa Farms LLCentered 2011-01-05
Primary law: CWA
Federal penalty: $10,750
Timeline (5 milestones)
- 2011-01-05NPDES Closed
- 2011-01-05Complaint Filed/Proposed Order
- 2011-01-05Final Order Issued
- 2011-01-05Enforcement Action Closed
- 2011-04-22Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 2600016231
- Case number
- 02-2011-3307
- Lead agency
- EPA
- Branch
- WGL
- EPA region
- 02
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Permit Violations
Sourced verbatim from EPA ECHO Enforcement Case Report for case 02-2011-3307 . Bulk data: ICIS-FEC download summary.