EPA v. Village of Castleton-on-Hudson
Final Order With Penalty
Case summary
Construction began September 8, 2008 prior to submittal of a Notice of Intent (NOI) on July 3, 2009. The reconstruction project at Green Avenue and Second Street was unpermitted for a total of 10 months.
Defendants (1)
- Village of Castleton-on-HudsonNamed in complaintNamed in settlement
Facilities (1)
VILLAGE OF CASTLETON-ON-HUDSON
GREEN AVENUE & SECOND STREET, VILLAGE OF CASTLETON-ON-HUDSON, NY, 12033
Registry ID: 110040083174
Statutes cited
- CWA 301 — NPDES Discharge without a Permit
Enforcement conclusions (1)
Village of Castleton-on-Hudsonentered 2009-12-10
Primary law: CWA
Federal penalty: $5,246
Timeline (5 milestones)
- 2009-12-10Complaint Filed/Proposed Order
- 2009-12-10Final Order Issued
- 2009-12-10NPDES Closed
- 2009-12-10Enforcement Action Closed
- 2010-03-15Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 1800082393
- Case number
- 02-2010-3310
- Lead agency
- EPA
- Branch
- WGL
- EPA region
- 02
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Discharge without a Permit