EPA v. Tonawanda Coke Corporation
Unilateral Administrative Order Without Adjudication
Case summary
Respondent failed to properly operate and maintain its facility; pipe leaks, corroded tanks, flow meters that were not calibrated, and the pretreatment flow meter was in the wrong location. Additionally, per DEC sampling, Respondent violated a Total Suspended Solids limitation at Outfall 002 in November 2009.
Defendants (1)
- Tonawanda Coke CorporationNamed in settlement
Facilities (1)
TONAWANDA COKE CORP
3875 RIVER ROAD, TONAWANDA, NY, 14150
Registry ID: 110000326772
Statutes cited
- CWA 301 — NPDES Discharge without a Permit
Enforcement conclusions (1)
Tonawanda Coke Corporationentered 2009-12-17
Primary law: CWA
Timeline (4 milestones)
- 2009-12-17NPDES Closed
- 2009-12-17Enforcement Action Closed
- 2009-12-17Final Order Issued
- 2009-12-22Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 1800067176
- Case number
- 02-2010-3012
- Lead agency
- EPA
- Branch
- WGL
- EPA region
- 02
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Discharge without a Permit
Sourced verbatim from EPA ECHO Enforcement Case Report for case 02-2010-3012 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.