Skip to main content
02-2010-1018Administrative - FormalClosedFY 2010· Region 02

EPA v. Slack Chemical Company, Inc.

Final Order No Penalty

Case summary

The inspection revealed that the Risk Management Plan (RMP) in place at the Slack facility located in Saratoga Springs, New York was deficient in numerous areas. In order to be in compliance with 40 CFR Part 68, the facility must conduct a hazard assessment; have updated process safety information; complete a Process Hazard Analysis (PHA); annually certify their SOPs, have a complete mechanical integrity program; have written management of change procedures, comply with the compliance audit requirements and have a developed and implemented employee participation program.

Defendants (1)

  • Slack Chemical Company, Inc.Named in settlement

Facilities (1)

  • SLACK CHEMICAL CO INC

    21 GRANDE BLVD, SARATOGA SPRINGS, NY, 12866

    Registry ID: 110017615856

Statutes cited

  • CAA 112[R][7]Prevention of Accidental Release/Risk Management Plans (RMPs)

Enforcement conclusions (1)

  • Slack Chemical Company, Inc.entered 2010-09-28

    Primary law: CAA

Timeline (3 milestones)

  • 2010-09-28Final Order Issued
  • 2010-09-28Enforcement Action Closed
  • 2010-09-30Enforcement Action Data Entered

Case metadata

EPA activity ID
2200015801
Case number
02-2010-1018
Lead agency
EPA
Branch
NYSUP
EPA region
02
Voluntary self-disclosure
No
Primary statute
Prevention of Accidental Release/Risk Management Plans (RMPs)

Sourced verbatim from EPA ECHO Enforcement Case Report for case 02-2010-1018 . Bulk data: ICIS-FEC download summary.