EPA v. Atlas Oil Company of Utica, Inc.
Final Order With Penalty
Case summary
The facility was inspected by EPA Contractors on December 15, 2008. The Inspection Checklist was reviewed by R Jamison, EPA. The contractor noted that there was a failure to appropriately monitor the tanks every 30 days. R Jamison concurred and issued a Field Citation from the desk.
Defendants (1)
- Atlas Oil Company of Utica, Inc.Named in complaintNamed in settlement
Facilities (1)
ATLAS OIL CO. OF UTICA, INC.
9598 STATE ROUTE 49, MARCY, NY, 13403
Registry ID: 110037957869
Statutes cited
- RCRA 9003 — UST Release Detection, Prevention, Correction Regulations
Enforcement conclusions (1)
Atlas Oil Company of Utica, Inc.entered 2009-03-18
Primary law: RCRA
Federal penalty: $50
Timeline (4 milestones)
- 2009-03-18Final Order Issued
- 2009-03-18Complaint Filed/Proposed Order
- 2009-03-18Enforcement Action Closed
- 2009-03-20Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 1400034550
- Case number
- 02-2009-7961
- Lead agency
- EPA
- Branch
- WTS
- EPA region
- 02
- Voluntary self-disclosure
- No
- Primary statute
- UST Release Detection, Prevention, Correction Regulations