02-2009-2000Administrative - FormalClosedFY 2009· Region 02

EPA v. The Mill, LLC (SB)

Final Order No Penalty

Case summary

Access Order issued to property owner to gain access to property in order to carry out sampling work in support of the remedial action at the Site. Access is needed to 1) take soil borings in the Property’s parking lot and analyze the samples taken to determine whether hazardous substances are present, and; 2) install temporary groundwater monitoring wells at the locations of two of the soil borings described above, and sample both these new temporary wells and a well which NMPC has already installed in the parking lot on the Property.

Defendants (1)

  • The Mill, LLC (SB)Named in settlement

Facilities (1)

  • NIAGARA MOHAWK POWER CORP. (SARATOGA SPRINGS PLANT)

    EAST AVENUE & EXCELCIOR RD, SARATOGA SPRINGS, NY, 12866

    Registry ID: 110009302986

Statutes cited

  • CERCLA 104E4Inspection and Samples

Enforcement conclusions (1)

  • The Mill, LLC (SB)entered 2009-08-06

    Primary law: CERCLA

Timeline (3 milestones)

  • 2009-08-06Final Order Issued
  • 2009-08-06Enforcement Action Closed
  • 2009-10-02Enforcement Action Data Entered

Case metadata

EPA activity ID
1800032223
Case number
02-2009-2000
Lead agency
EPA
Branch
NYSUP
EPA region
02
Voluntary self-disclosure
No
Primary statute
Inspection and Samples

Sourced verbatim from EPA ECHO Enforcement Case Report for case 02-2009-2000 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.