The facility was inspected by EPA Contractors on December 17, 2008. The contractor noted that there was a failure to adequately operate the Interstitial Monitoring, and proper operation of corrosion protection. EPA reviewed the Inspection Checklist and issued a Field Citation from the desk.
Defendants (1)
- Lawrence Paul Fuels (SB)Named in complaintNamed in settlement
Facilities (1)
LAWRENCE PAUL FUELS
2 EAST MAIN STREET, MOHAWK, NY, 13407
Registry ID: 110037958877
Statutes cited
- RCRA 9003 — UST Release Detection, Prevention, Correction Regulations
Enforcement conclusions (1)
Lawrence Paul Fuels (SB)entered 2009-05-26
Primary law: RCRA
Federal penalty: $450
Timeline (4 milestones)
- 2009-05-26Final Order Issued
- 2009-05-26Complaint Filed/Proposed Order
- 2009-05-26Enforcement Action Closed
- 2009-06-02Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 1400047000
- Case number
- 02-2009-0505
- Lead agency
- EPA
- Branch
- WTS
- EPA region
- 02
- Voluntary self-disclosure
- No
- Primary statute
- UST Release Detection, Prevention, Correction Regulations