EPA v. Denison Enterprises (SB)
Final Order With Penalty
Case summary
Inspection found that facility did not conduct cathodic protection test on sacrifical anodes and did not do annual test for automatic line leak detectors. Field citation II-UST-FC-322EC was issued for violations of 40 CFR 280.31(b); failure to ensure proper cathodic protection system and 40 CFR 280.41(b)(1(ii) failure to have annual line tightness tests or perform monthly monitoring on pressurized piping. Tests were subsequently done and facility passed
Defendants (1)
- Denison Enterprises (SB)Named in complaintNamed in settlement
Facilities (1)
MARK E. DENISON DBA DENISON ENTERPRISES
86 NORTH MAIN STREET, CASSADAGA, NY, 14718
Registry ID: 110030906401
Statutes cited
- RCRA 9003[C][3]-[4] — UST Release Detection, Prevention, Correction
Enforcement conclusions (1)
Denison Enterprises (SB)entered 2008-02-20
Primary law: RCRA
Federal penalty: $450
Timeline (4 milestones)
- 2008-02-20Complaint Filed/Proposed Order
- 2008-02-20Enforcement Action Closed
- 2008-02-20Final Order Issued
- 2008-03-07Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 600084777
- Case number
- 02-2008-7935
- Lead agency
- EPA
- Branch
- WTS
- EPA region
- 02
- Voluntary self-disclosure
- No
- Primary statute
- UST Release Detection, Prevention, Correction
Sourced verbatim from EPA ECHO Enforcement Case Report for case 02-2008-7935 . Bulk data: ICIS-FEC download summary.