EPA v. Inmobiliaria Unibon, Inc. (SB)
Final Order With Penalty
Case summary
RESPONDENT WAS FOUND IN VIOLATION OF THE NPDES STORM WATER CONSTRUCTION GENERAL PERMITS, FOR FAILURE TO FILE A NPDES PERMIT, DEVELOP AND IMPLEMENT A SWPPP, FAILURE TO CONDUCT INSPECTIONS AND FAILURE TO POST A SIGN. CONSENT AGREEMENT AND FINAL ORDER for Respondent did not submit an individual NPDES permit application at least ninety (90) days before the date on which construction activities commenced as required by 40 C.F.R. § 122.21, nor did it file a complete and accurate Notice of Intent form prior to commencement of construction activities as required by Part 2 of the Construction Permit; and that Respondent discharged pollutants into waters of the United States without authorization of an NPDES permit, in violation of Section 301(a) of the Act, 33 U.S.C. § 1311.
Defendants (1)
- Inmobiliaria Unibon, Inc. (SB)Named in complaint
Facilities (1)
RIBERAS DE UNIBON CONSTRUCTION PROJECT
STATE ROAD 159, KM. 5.8, UNIBON WARD, MOROVIS, PR, 00687
Registry ID: 110028077952
Statutes cited
- CWA 301/402 — NPDES Permit Violations
Enforcement conclusions (1)
Inmobiliaria Unibon, Inc. (SB)entered 2009-04-01
Primary law: CWA
Federal penalty: $87,000
Timeline (5 milestones)
- 2008-05-13Complaint Filed/Proposed Order
- 2008-05-14Enforcement Action Data Entered
- 2009-04-01NPDES Closed
- 2009-04-01Enforcement Action Closed
- 2009-04-01Final Order Issued
Case metadata
- EPA activity ID
- 1000001552
- Case number
- 02-2008-3457
- Lead agency
- EPA
- Branch
- WGL
- EPA region
- 02
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Permit Violations
Sourced verbatim from EPA ECHO Enforcement Case Report for case 02-2008-3457 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.