02-2008-3325Administrative - FormalClosedFY 2008· Region 02

EPA v. Centro Medico Del Turabo, Inc.

Final Order With Penalty

Case summary

Centro Medico del Turabo, Inc. is expanding its hospital/health facilities in Caguas, Puerto Rico. There is one Construction General Permit (CGP) for the entire 28.30 site; however, because different portions of the site are being built by different General Contractors, separate Storm Water Pollution Prevention Plans (SWPPPs) were prepared for each construction area. Penalty payment.

Defendants (3)

  • Centro Medico Del Turabo, Inc.Named in complaintNamed in settlement
  • Beyley Construction Corp.Named in complaintNamed in settlement
  • Caribbean Construction Technologies, Inc.Named in complaintNamed in settlement

Facilities (1)

  • HERMINIO COTTO (MADRID PLAZA)

    INT. PR9919 AND PR-189, JUNCOS, PR, 00777

    Registry ID: 110024531639

Statutes cited

  • CWA 308Information Request, Records, Entry
  • CWA 301/402NPDES Permit Violations

Enforcement conclusions (1)

  • Centro Medico Del Turabo, Inc.entered 2008-11-24

    Primary law: CWA

    Federal penalty: $8,850

Timeline (5 milestones)

  • 2008-09-24Complaint Filed/Proposed Order
  • 2008-09-25Enforcement Action Data Entered
  • 2008-11-24Final Order Issued
  • 2008-11-24Enforcement Action Closed
  • 2008-11-24NPDES Closed

Case metadata

EPA activity ID
1400007633
Case number
02-2008-3325
Lead agency
EPA
Branch
WGL
EPA region
02
Voluntary self-disclosure
No
Primary statute
Information Request, Records, Entry

Sourced verbatim from EPA ECHO Enforcement Case Report for case 02-2008-3325 . Bulk data: ICIS-FEC download summary.