02-2006-3307Administrative - FormalClosedFY 2006· Region 02

EPA v. HBA Contractors, Inc., Fermin Delgado-Diaz Public School

Final Order With Penalty

Case summary

The site is 4.05 acres. There were no storm water controls in place and they did not have a Storm Water Pollution Prevention Plan. The facility submitted an NOI obtained a Permit and implemented storm water controls and is now in compliance.

Defendants (1)

  • HBA Contractors Inc Fermin Delgado-Diaz P.S.Named in complaintNamed in settlement

Facilities (1)

  • PRPBA-FERMIN DELGADO-DIAZ SCHO

    STATE ROAD PR-950 KM 3.5, NAGUABO, PR, 00718

    Registry ID: 110009814264

Statutes cited

  • CWA 301NPDES Discharge without a Permit

Enforcement conclusions (1)

  • HBA Contractors, Inc., Fermin Delgado-Diaz Public Schoolentered 2006-06-14

    Primary law: CWA

    Federal penalty: $8,500

Timeline (4 milestones)

  • 2006-04-07Complaint Filed/Proposed Order
  • 2006-05-02Enforcement Action Data Entered
  • 2006-06-14Enforcement Action Closed
  • 2006-06-14Final Order Issued

Case metadata

EPA activity ID
176520
Case number
02-2006-3307
Lead agency
EPA
Branch
WGL
EPA region
02
Voluntary self-disclosure
No
Primary statute
NPDES Discharge without a Permit