Skip to main content
02-2005-3233Administrative - FormalClosedFY 2005· Region 02

EPA v. Villas de la Serrania

Unilateral Administrative Order Without Adjudication

Case summary

Based on a CEI conducted in March 2005, in the site is approximately 54.5 acres and has construction general permit. The site fences were not installed or maintained properly, because they were not keyed into the soil. No sediment basins were installed. No storm water pollutin prevention plan was available during the inspection nor submitted afterwards. The facility will be required to develop and implement a SWPPP and implement Storm Water BMPs.

Defendants (2)

  • Villas de la SerraniaNamed in settlement
  • Lluna Develop Corp. & Gurabo MA Inc. (Monte Alto)Named in settlement

Facilities (1)

  • VILLAS DE LA SERRANIA

    STATE ROAD PR 189 KM. 4.0, GURABO, PR, 00725

    Registry ID: 110022290180

Statutes cited

  • CWA 301/402NPDES Permit Violations

Enforcement conclusions (1)

  • Villas de la Serraniaentered 2005-08-23

    Primary law: CWA

Timeline (3 milestones)

  • 2005-08-23Enforcement Action Closed
  • 2005-08-23Final Order Issued
  • 2005-09-16Enforcement Action Data Entered

Case metadata

EPA activity ID
156797
Case number
02-2005-3233
Lead agency
EPA
Branch
WGL
EPA region
02
Voluntary self-disclosure
No
Primary statute
NPDES Permit Violations