This Administrative Order is to allow the permittee to conduct a pilot test at a cooling tower to test whether changes in chemical operation will improve the unit operation and quality of the cooling water.
Defendants (1)
- PREPA - Palo Seco Power PlantNamed in settlement
Facilities (1)
PUERTO RICO ELECTRIC PWR AUTH
PALO SECO STEAM PLANT, TOA BAJA, PR, 00758
Registry ID: 110000607950
Statutes cited
- CWA 301 — NPDES Discharge without a Permit
Enforcement conclusions (1)
PREPA - Palo Seco Power Plantentered 2004-10-26
Primary law: CWA
Timeline (4 milestones)
- 2004-10-26Enforcement Action Closed
- 2004-10-26Final Order Issued
- 2004-10-26NPDES Closed
- 2004-11-03Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 135271
- Case number
- 02-2005-3002
- Lead agency
- EPA
- Branch
- CT
- EPA region
- 02
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Discharge without a Permit