02-2004-3060Administrative - FormalClosedFY 2004· Region 02

EPA v. PRASA Juncos WWTP

Unilateral Administrative Order Without Adjudication

Case summary

Within thirty (30) calendar days of receipt of the ORDER, PRASA shall submit a compliance plan to EPA that outlines a schedule, for the completion of all the permanent repairs needed to correct the deficiencies found at the Juncos WWTP during the EPA's CEI of January 26, 2004. The schedule shall not contain dates beyond one hundred and twenty (120) calendar days of receipt of this ORDER. All the treatment modules, pumps, controllers, mechanical and electrical equipment, including, but not limited to, switches, float controllers, alternate power generators, lighting and safety equipment should be in full operational condition.

Defendants (1)

  • PRASA Juncos WWTPNamed in settlement

Facilities (1)

  • PRASA JUNCOS STP

    END OF DELFAUS ST, JUNCOS, PR, 00666

    Registry ID: 110013696018

Statutes cited

  • CWA 301NPDES Discharge without a Permit

Enforcement conclusions (1)

  • PRASA Juncos WWTPentered 2004-04-16

    Primary law: CWA

Timeline (3 milestones)

  • 2004-04-16Enforcement Action Closed
  • 2004-04-16Final Order Issued
  • 2004-06-14Enforcement Action Data Entered

Case metadata

EPA activity ID
120961
Case number
02-2004-3060
Lead agency
EPA
Branch
CT
EPA region
02
Voluntary self-disclosure
No
Primary statute
NPDES Discharge without a Permit

Sourced verbatim from EPA ECHO Enforcement Case Report for case 02-2004-3060 . Bulk data: ICIS-FEC download summary.