EPA v. PRASA NARANJITO WTP
Unilateral Administrative Order Without Adjudication
Case summary
****** FACILITY HAD A PREVIOUS ORDER ON CONSENT (CWA-02-1995-180) WHICH REQUIRED PRASA TO START THE CONSTRUCTION OF A SLUDGE TREATMENT SYSTEM BY 3/1/97 AND END SUCH CONSTRUCTION BY 5/30/98. PRASA FINISHED THE CONSTRUCTION ON JUNE 2000 AND HAVE NOT OPERATED THE SLUDGE TREATMENT SYSTEM SINCE THAT DATE. THE PURPOSE OF THIS ORDER IS TO HAVE PRASA OPERATE THE SYSTEM AND COMPLY WITH ALL TERMS AND CONDITIONS OF THE PERMIT.
Defendants (1)
- PRASA NARANJITO WTPNamed in complaintNamed in settlement
Facilities (1)
PRASA WTP NUEVA (NARANJITO) FILTRATION
RD 164 & 825 INTR, NARANJITO, PR, 00719
Registry ID: 110006693961
Statutes cited
- CWA 301 — NPDES Discharge without a Permit
Enforcement conclusions (1)
PRASA NARANJITO WTPentered 2001-08-14
Primary law: CWA
Timeline (3 milestones)
- 2001-08-14Enforcement Action Closed
- 2001-08-14Final Order Issued
- 2001-08-21Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 8383
- Case number
- 02-2001-3061
- Lead agency
- EPA
- HQ division
- WAT
- Branch
- CT
- EPA region
- 02
- Multimedia
- No
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Discharge without a Permit
Sourced verbatim from EPA ECHO Enforcement Case Report for case 02-2001-3061 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.