01-2027-2001Administrative - FormalFinal Order IssuedFY 2027· Region 01

EPA v. WOODSTOCK NH WASTEWATER TREATMENT FACILITY

Final Order No Penalty

Case summary

On October 2, 2026, the Region entered into an administrative order on consent ( AOC ) with the Town of Woodstock, New Hampshire requiring the Town to comply with the monitoring requirements for total copper in the 2023 NPDES Permit, optimize the removal of total copper from its wastewater treatment plant effluent, and submit annual Copper Optimization Reports until the Town is issued a renewed or modified permit. The Order also requires the Town to submit a Collection System Operations and Maintenance Plan by December 31, 2026. The Region worked in close coordination with the New Hampshire Department of Environmental Services in this matter.

Defendants (1)

  • Town of Woodstock, NHNamed in complaintNamed in settlement

Facilities (1)

  • WOODSTOCK W W T P

    ROUTE 175 OLD DUMP ROAD, NORTH WOODSTOCK, NH, 03262

    Registry ID: 110009840084

Statutes cited

  • CWA 301/402 — NPDES Permit Violations

Enforcement conclusions (1)

  • WOODSTOCK NH WASTEWATER TREATMENT FACILITYentered 2026-10-02

    Primary law: CWA

Timeline (3 milestones)

  • 2026-10-02Complaint Filed/Proposed Order
  • 2026-10-02Final Order Issued
  • 2026-10-06Enforcement Action Data Entered

Case metadata

EPA activity ID
3605238219
Case number
01-2027-2001
Lead agency
EPA
EPA region
01
Voluntary self-disclosure
No
Primary statute
NPDES Permit Violations