EPA v. R.A.D. SPORTS (MONTROSE SCHOOL)
Case summary
On September 29, 2026, EPA-Region 1 entered into an expedited settlement agreement (Agreement) with R.A.D. Sports, LLC ( Montrose School Campus Improvement Project ), addressing violations of the General Permit for Discharges from Construction Activities (CGP) at the Montrose School Campus Improvement Project site in Medfield, Massachusetts. On March 13, 2026, EPA Region 1 conducted an inspection at the Montrose School Campus and observed failures to comply with the permit. Pursuant to the Agreement, R.A.D. Sports, LLC will pay a $4,500 penalty. EPA implements the National Pollutant Discharge Elimination System program in Massachusetts. The case team consulted with the Massachusetts Department of Environmental Protection on this matter.
Defendants (1)
- R.A.D. SportsNamed in complaintNamed in settlement
Facilities (1)
MONTROSE SCHOOL CAMPUS IMPROVEMENT PROJECT
29 NORTH STREET, MEDFIELD, MA, 02052
Registry ID: 110043926357
Statutes cited
- CWA 301/402 — NPDES Permit Violations
Enforcement conclusions (1)
R.A.D. SPORTS (MONTROSE SCHOOL)entered 2026-09-29
Primary law: CWA
Federal penalty: $4,500
Timeline (3 milestones)
- 2026-09-29Complaint Filed/Proposed Order
- 2026-09-29Final Order Issued
- 2026-10-01Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 3605234074
- Case number
- 01-2026-2042
- Lead agency
- EPA
- EPA region
- 01
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Permit Violations
Sourced verbatim from EPA ECHO Enforcement Case Report for case 01-2026-2042 . Bulk data: ICIS-FEC download summary.