EPA v. NEXTGRID PATRIOTS LLC
Case summary
On September 8, 2026, EPA-Region 1 entered into an expedited settlement agreement (Agreement) with NextGrid Patriots, LLC ( Pond Street Solar Project ), addressing violations of the General Permit for Discharges from Construction Activities (CGP) at the Pond Street Solar Project site in Norfolk, Massachusetts. On March 30, 2026, EPA Region 1 conducted an inspection at Pond Street Solar Project and observed that the Respondent had failed to obtain permit coverage for stormwater discharges between March 2025 to March 2026. Pursuant to the Agreement, NextGrid Patriots, LLC will pay a $14,400 penalty. EPA implements the National Pollutant Discharge Elimination System program in Massachusetts. The case team consulted with the Massachusetts Department of Environmental Protection on this matter.
Defendants (1)
- NEXTGRID PATRIOTS LLCNamed in complaintNamed in settlement
Facilities (1)
NEXTGRID PATRIOTS LLC
100 POND STREET, NORFOLK, MA, 02056
Registry ID: 110072160988
Statutes cited
- CWA 301/402 — NPDES Permit Violations
Enforcement conclusions (1)
NEXTGRID PATRIOTS LLCentered 2026-09-08
Primary law: CWA
Federal penalty: $14,400
Timeline (3 milestones)
- 2026-09-08Complaint Filed/Proposed Order
- 2026-09-08Final Order Issued
- 2026-09-10Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 3605151580
- Case number
- 01-2026-2036
- Lead agency
- EPA
- EPA region
- 01
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Permit Violations
Sourced verbatim from EPA ECHO Enforcement Case Report for case 01-2026-2036 . Bulk data: ICIS-FEC download summary.