Skip to main content
01-2025-2093Administrative - FormalFinal Order IssuedFY 2025· Region 01

EPA v. THE CAMELOT - REBECCA ROAD (REMP INC)

Case summary

On September 30, 2025, EPA Region 1 entered into an expedited settlement agreement (Agreement) with REPM, Inc., addressing violations of the General Permit for Discharges from Construction Activities (CGP) at The Camelot site in Northbridge, Massachusetts. On December 18, 2024, EPA Region 1 conducted an inspection at The Camelot site and observed that the facility had failed to apply for permit coverage. After the inspection, Facility applied for and obtained permit coverage. Pursuant to the Agreement, REPM, Inc. will pay a $4,200 penalty. EPA implements the National Pollutant Discharge Elimination System program in Massachusetts. The case team consulted with the Massachusetts Department of Environmental Protection on this matter.

Defendants (1)

  • REMP, Inc.Named in complaintNamed in settlement

Facilities (1)

  • THE CAMELOT - REBECCA ROAD

    REBECCA ROAD, WHITINSVILLE, MA, 01588

    Registry ID: 110071885051

Statutes cited

  • CWA 301NPDES Discharge without a Permit

Enforcement conclusions (1)

  • THE CAMELOT - REBECCA ROAD (REMP INC)entered 2025-09-30

    Primary law: CWA

    Federal penalty: $4,200

Timeline (3 milestones)

  • 2025-09-30Complaint Filed/Proposed Order
  • 2025-09-30Final Order Issued
  • 2025-09-30Enforcement Action Data Entered

Case metadata

EPA activity ID
3604560787
Case number
01-2025-2093
Lead agency
EPA
EPA region
01
Voluntary self-disclosure
No
Primary statute
NPDES Discharge without a Permit

Sourced verbatim from EPA ECHO Enforcement Case Report for case 01-2025-2093 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.